"Better Insight Through Analysis"

 

 
Material Integrity Solutions, Inc.
 

For specific  information on any of our projects, please contact us at 510.594.0300 - Ext. 201 - Thank you for your interest.

2007 -     2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..

Design & Engineering Services - ~733kW Solar Tracker Array System - Water Treatment Plant, Yuba City, CA

 

Design foundations for ground-mounted solar tracker array systems requiring conditions for existing "retention pond" and wind speed of ~75mph.  Scope of services will include but are not limited to Value Engineering Phase, Design Foundations for Array's Pedestals/Electrical Equipment.  Development of "Permit, Construction and As-built" drawings.  April  2007 is the projected completion date.

 

Design & Engineering Services - ~500kW Solar Systems - Wind Farm, Ellington, WA

 

Design & Engineering Services for Installation of 500kW Ground Mounted PV Solar Systems at a Wind Farm, in Ellington, WA . Electrical equipment (inverters/transformers, switches, etc.) for these systems will be placed and supported. MIS will be developing conceptual designs, foundation/structural plans, connection methods, electric title, specs, one and three line drawings, grounding plan/details, wire/conduit sizing/list, plan and details as well as wiring designs.

 

Corrosion and Inspection - Hot Water Loop,  Wastewater Pollution Control Plant, CA

 

 Per client's request, MIS will be performing corrosion and inspection procedures at the site to determine the extent of internal corrosion damage and failures to areas previously replaced. A condition assessment of this system will be performed to determine its reliability and to find out critical areas of piping which may need immediate attention and/or replacing.  In addition, methods will be developed to monitor/mitigate future damage in this line to ensure future reliable operation.   Findings will be summarized and presented outlining the approach/results in a comprehensive report.

 


Relay Coordination Study - San Francisco, CA

 

Client's submittal of a 430C, Short Circuit Coordination Study (SCCS) was rejected due to its being unacceptable to PG&E. the study did not show (.2) seconds of separation between the Breaker and the PG&E interrupter. MIS was selected and performed the task of a Short Circuit Coordination Study, with the goal of finding ways to work within PG&E's limitations.  MIS studied the problem and developed basic parameters which were entered into a curve plotting software.  Several scenarios were developed and implemented which helped resolve the problem to client's and PG&E's satisfaction.

 

 

  2006     2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..

 

 Electrical Power Failure System Evaluation & Improvements - San Lorenzo, CA

 

Conduction and evaluation of the electrical power systems at a  RAS/WAS facility, in San Lorenzo, CA. This evaluation includes a forensic/failure analysis of power failure events where a number of transient voltage surge suppressors (TVSS) failed. This project is being conducted in two phases, phase I, Data Gathering/Evaluation and Phase II, Design Improvements/Remedial Actions.

Status:  Phase I - Completed November 2006 - Phase II - January 2007.

 

 Design & Engineering Services - Solar PowerTracker System -  Spain & South Korea

 

Technical Design & Engineering support for pedestal foundations at various PV PowerTracker array systems in Trujillo/ Jumilla, Spain and Mun-Gyeong/ Nok-Mun Ri, South Korea. The scope of work includes review of documents (surveys, geotech studies, plans, etc.)  providing comments, identifying additional required information, design of foundations for array and motor pedestals. Two types of foundations (“pier” and “mat”) will be considered and proposed for these sites. 

 

Fabrication and Consultation - Sagging Line Mitigator (SLiM) Device

 

Fabrication, delivery and consultation services during installation process of Custom and Standard SLiM Devices for two major utility clients,  ESKOM/TAP in Midrand, South Africa and CESI RICERCA SpA in Milan, Italy.  The devices have been purchased by Power Transmission Solutions, Inc. (PTS) www.ptransolutions.com and currently are being tested and utilized by ESKOM.  CESI RICERCA SpA is expected to release funding during first quarter 2007.

 

Design & Engineering  Services -  Ground-Mounted Solar Tracker Array Systems, Sonoma, CA

 

Design foundations for the ground-mounted solar tracker array systems in Sonoma, CA to include the following criteria:

Design foundations for array’s pedestals, design foundation (mat/slab-on-grade) for electrical equipment for the  PV system,
design foundation (mat/slab-on-grade) for utility switchgear and to  provide support during construction, as-built review/approval (from contractor redlines) for MIS details.

 

 Design & Engineering Services - PowerTracker Foundations - Wastewater Treatment Plant Hill County , CA

The project consist of six (6) PowerTracker arrays (584kW) - each array containing a number of pedestals that support the PowerTracker main rotating members (torque tubes) and one pedestal to support the motor drive system.  Brief scope of work will include value-engineering phase, design foundations for array's pedestals, design foundation (mat/slab-on-grade) for electrical equipment for the PV system, issue for “Permit”, " Construction" and "As-Built" drawings.

 

Design & Engineering Services - ~3.8MW Landfill Gas Fueled Power Plant - Pittsburg, CA

 

Design a new ~3.8 MW landfill gas fueled power generation plant in Pittsburg, CA consisting of two (2) GE/Jenbacher 616 engines with their generators. In addition to providing assistance in pre-purchase of major equipment, and preparation of design/construction documents, MIS assisted the client in preparation, submission and completion of the Interconnection Agreement for the landfill to gas to electricity facility.

Design & Engineering Services - 7.6MW Landfill Gas Fueled Power Plant  - Valencia, CA

Prepare, submit and obtain pre-approval for an interconnect agreement for Chiquita Canyon Landfill Gas Project  to include development of  1-line, site plan, title drawing for the proposed facility which will consist of two Solar gas turbines (~7.6MW) , obtain dynamic models, etc., from equipment suppliers in preparation of the application. Complete and submit CAISO paperwork for including the new plant on their system and assign proper “code” names. 

 Value Engineering Services - Hopper Bolt Failure - Watsonville, CA

Assess bolt failure attributed to fatigue mechanism with corrosion as a potential contributor.  Examine source of excessive loading due to vibration/swinging of the hopper during travel.  Develop a preventive solution for future failures by addressing corrosion-fatigue mechanism.


Value Engineering Services , San Francisco, CA

 

Provide alternative design for buried pipe sewer line and support system to carry vertical downward force of the soil above and to withstand uplift forces due to buoyancy effect.  Since the completion of the piping analysis/solution phase of the project, MIS continues to provide design/analysis/solution support in various other aspect of the project to include design of an alternative to Metal Fence Support, Car Puller Pit redesign, OCS Pole change, Seismic Zone 4 compliance of a Fiberglass Cable Tray System.

 

Failure Analysis and Solutions for an Engine with Exhaust Heat Recovery System, San Francisco, CA

 

Develop an understanding of the loads and failure mechanism of the exhaust system, evaluate its current design for such conditions, and develop recommendations/fixes to the original design.

 

 

 PowerTracker PV Array Systems - Las Vegas, NV

 

Develop conceptual designs for Fixed Canopy and Long-Span Tracker Systems, various iterations for "straight" and "curved" PowerTracker Systems over parking lots and water reservoirs. 

 

Model and Analyze Canopy Designs - Las Vegas NV

 

Develop and analyze single and double cantilever canopy designs for supporting bi-facial solar panels over parking structure on top of existing reservoir.  The modeling will explore various member sizing and connection types to provide a workable and efficient design.

 

2005    2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..    - Back to Top  

Project:  Design & Engineering -  3MW Landfill Gas Project, Santa Cruz, CA

Period:  January 2005 -  April 2006

Description:  Design New 3MW Landfill Gas Fueled Power Plant. 

Firm's Role:  Prepare Conceptual Design &  Design Package to include support for completing the Electrical Interconnect Application, assist in pre-purchase of major equipment and preparation of design/construction documents.

Status: Project Complete

Project:   Design & Engineering - 11.2MW Landfill Gas Project, Half Moon Bay, CA

Period:  April 2005 - Present
Description:  Design New ~11.2 MW Landfill Gas Fueled Power Plant with six Jenbacher Model #616 Landfill Gas Engines and the required Substation.
Firm's Role:  Prepare Conceptual Design & Design Package to include completing and supporting the Electrical Interconnect Applications with both CAISO & PG&E.  Assist in selection of equipment and preparation of Construction Documents. 

Status:   In progress


Project: Design & Engineering  - 1MW Fuel-Cell Power Generation Plant, Santa Rita Jail, Dublin, CA

 

Period:   May 2005 - August 2005

Description:  Design/Construction Package for a 1MW Fuel-Cell Power Plant at the Santa Rita Jail Facility. 

Firm's Role:  Prepare Design & Construction Documents to include completing & submitting of the Electrical Interconnect Application.

Status: Project complete

 

Project:  Analysis & Solutions - Cogeneration Plant Crockett, CA

 

Period:  January 2005 - May  2005

Description:  Develop replacement support for the three hangers on Main Steam Line with crushed installation supports.

Firm's Role:  Evaluation of existing conditions, design new hangers, develop replacement/installation construction at the pipe metal, provide field engineering support.

Status:  Project complete

Project:  Analysis & Solutions - Cogeneration Plant , Crockett, CA

Period: January 2005 - May  2005

Description:  Evaluate the extraction steam line between turbine connection to valve for its current condition and provide long-term improvements for the affected areas.

Firm's Role:  Observation, high bending stress analysis, welding x-rays and  analysis, cracks and failure analysis and causes, repair plans/drawings.  Development of upgrade plans, field support engineering and implementation of repair plans.

Status:  Project complete

 

Project: Consulting Support - Generic Peaking/Islanding Generation Unit Specification

 

Period:  March 2005 - September 2005

Description:  Develop a generic performance-type specification for Combustion Turbine Generation Units to be used for Peaking and Standby Power.

Firm's Role:  Development of Generic CT-Scope, Bid Selection Criteria and evaluate bid responses, present Bid Recommendation Report and conduct meetings on site.

Status:  Project complete

 

Project:  Single PowerTracker Solar  System  over  Parking Lot Structure

 

Period:  February 2005 - July  2005

Description:  Design/engineer supporting structure for 1080 Sanyo-190 PV modules to be located above an existing outdoor/ground based parking lot.

Firm's Role:  Design foundations and steel structure to support the system up to the connections to PowerTracker pedestal to include Construction Drawings.

Status:  Project complete

2004   2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  - Back to Top   

Project:  Engineering Consulting Support -  Clearwater Cogeneration & Biosolids Project

Period: May 2004 - August 2004

Description: On-site Technical & Administrative Support -  Construction Management Operations
Firm’s Role: To provide on-site engineering services through local engineering office personnel.
Status: Project complete

Project:  Analysis and Solutions/Engineering - NGMS Facility Steam Piping
Period: January 2004 - September 2004
Description: Piping system analysis; design modifications.
Firm’s Role: To provide piping system engineering and design services.
Status: Project complete

Project:  Analysis and Solutions/Engineering  - Evaluation of the underground hot water distribution piping
Period: April 2004 – May 2004
Description: Evaluate the existing condition of underground hot water distribution piping.
Firm’s Role: To identify causes of failures on branch lines and recommend preventive measures.
Status: Project complete

Project : Design & Engineering -  Altamont Landfill Power & Communication Line Upgrade
Period: May 2004 - December 2004
Description: Design/Engineering modifications of the power lines for the Altamont Pass Generation facility to facilitate the planned expansion of the landfill.
Firm’s Role: To identify electrical engineering and design services.
Status: Project complete

Project: Design & Engineering  - Solar - Chevron De Anza College Parking Garage - Roof Level
Period: May 2004 – May 2005
Description: Installation of Power Tracker Canopy system Using Sanyo-190 PV Arrays
Firm’s Role: To provide civil/structural engineering to design for construction a supporting frame for the photovoltaic panels and its attachment to the existing roof structure.
Status:  Project complete

Project : Design & Engineering - Solar - Chevron Foothill College Parking
Period: May 2004 – May 2005
Description: Installation of Fixed Canopy System Using Mitsubishi-165 PV Arrays
Firm’s Role: To provide civil/structural engineering to design for construction a supporting frame for the photovoltaic panels and its attachment to the existing roof structure.
Status:  Project complete

Project: Design & Engineering - Solar -  West Sacramento USPS carport Solar
Period: March 2004 – September 2004
Description: Installation of 360 Sharp 165MW PV Modules on two Canopy/Shade Structures
Over the Solano County Parking Structure in Fairfield, CA.
Firm’s Role: To provide civil/structural engineering to design for construction a supporting
frame for the photovoltaic panels and its attachment to the existing roof structure.
Status: Project complete

Project: Design & Engineering - Solar - Structural Supports – For PV Panel Assembly in Hawaii
Period: January 2004 – April 2004
Description: Installation of a phototvoltaic power system building roof.
Firm’s Role: To provide civil/structural engineering to design for construction a supporting frame for the photovoltaic panels and its attachment to the existing roof structure.
Status: Project complete

Project:  Design& Engineering - Solar -  Structural Supports - St. Francis Winery
Period: January 2004 – May 2004
Description: Installation of a phototvoltaic power system winery roof.
Firm’s Role: To provide civil/structural engineering to design for construction a supporting frame for the photovoltaic panels and its attachment to the existing roof structure.
Status: Project complete
 

 2003    2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  - Back to Top      

Project: Design & Engineering - Redesign of an 8 MW Power Plant in Big Bear Lake, CA
Period: August 2003 – June 2004
Description: Redesign of a previously completed project from 2001 to improve aesthetic quality of facility structure.
Firm’s Role: To provide civil, architectural, mechanical and electrical engineering services along with field and logistical support for the redesign of the facility structure and affected mechanical and electrical systems.
Status: Project complete.

Project: Design and Engineering -  2.4 MW Landfill Gas Generating Facility for Waste Management, Inc. in Simi Valley, CA
Period: February - August 2003
Description: Green field construction of multiple modularized reciprocating gas engines to provide base load power consuming gas produced by the landfill.
Firm’s Role: To provide civil, electrical, and mechanical engineering services for the design and permitting of the power plants.
Status: Project complete.

Project: Design & Engineering  -  3.6 MW Landfill Gas Generating Facility for Waste Management, Inc. near Corona, CA
Period: February - August 2003
Description: Green field construction of multiple modularized reciprocating gas engines to provide base load power consuming gas produced by the landfill.
Firm’s Role: To provide civil, electrical, and mechanical engineering services for the design and permitting of the power plants.
Status: Project complete.

Project: Design & Engineering -  4.2MW 600 Ton Cogeneration Facility for DST Reality in El Dorado Hills, CA

Period: January 2003 to June 2004
Description: Green field construction of a dual engine facility with heat recovery to produce up to 600 tons of chilled water through absorption chilling.
Firm’s Role: To provide civil, structural and mechanical engineering services for the design and permitting of the Cogeneration plant.
Status: Project complete.

Project: Design & Engineering -  1 MW 100 Ton Cogeneration Facility for an Office Building High Rise in San Francisco, CA
Period: November 2002 - Present
Description: Construction of a three-engine basement facility with heat recovery to produce up to 100 tons of chilled water through absorption chilling.
Firm’s Role: To provide civil, structural, electrical and mechanical engineering services for the design and permitting of the Cogeneration plant.
Status: Engineering and permitting complete construction underway as of September.

Project: Engineering and Specification -  Sludge Piping Modernization Project
Period: April 2003 – June 2004
Description: Replacement of aging and deteriorating sludge piping systems with current modern standards for waste piping for better performance and reliability.
Firm’s Role: To provide civil engineering services to prepare drawings and technical specifications for a public for-bid package.

Project: Development of a High Energy Piping Survey -  Selected Piping Systems 
Period: June 2003– October 2003
Description: Initial development of a HEP Program for two critical piping systems at Crockett Cogen’s gas fired 240 MW combined cycle plant.
Firm’s Role: To provide expertise and guidance in collecting plant data, establishing a database of component information, screening critical piping systems for inspection, and compiling all information into an interim report to be part of a future manual which will provide for program guidance.
Status: Final report completed and issued.

Project: Design  - Solar - Structural Supports – For 5 MW PV Panel Assembly
Period: December 2003 – Present
Description: Installation of a phototvoltaic power system over a field.
Firm’s Role: To support high voltage design for a large solar system
Status: Design in progress.

Project: Design - Solar - Structural Supports – For PV Panel Assembly in Chico, CA
Period: November 2003 – December 2003
Description: Installation of a phototvoltaic power system over the upper level of parking structure.
Firm’s Role: To provide civil/structural engineering to design for construction a supporting frame for the photovoltaic panels and its attachment to the existing parking structure.
Status: Project complete.

Project: Design - Solar - Structural Supports – Sanyo PL Tracker Assembly in San Diego, CA
Period: September 2003 – November 2003
Description: Installation of a phototvoltaic power system over the Commercial Office Bldg Parking.
Firm’s Role: To provide civil/structural engineering to design for construction a supporting frame for the photovoltaic panels and tracking assembly.
Status: Project Complete

Project: Design  - Solar - Structural Supports – Astropower APX-130 PV Panels at Applied Bio Systems Building
Period: August 2003 – September 2003
Description: Installation of a phototvoltaic power system on the roof of a commercial office building.
Firm’s Role: To provide civil/structural engineering to design for construction a supporting frame for the photovoltaic panels and its attachment to the existing roof structure.
Status: Project Complete

Project: Research & Development - Sagging Line Mitigator Field Demonstration (SLiM)
Period: April 2003 - Present
Description: Utility demonstration of the production model of the SLiM device.
Firm’s Role: Engineering design of the production SLiM model as well technical and logistical support of the utility demonstration.
Status: Work in progress.
 

2002  2007 - 2006 -  2005 -   2004 -  2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/.. - Back to Top      

 

Project: Engineering - Development of a High Energy Piping Program

Dates: July 2002 to October 2002

Description: Development of HEP Program for four critical piping systems at a coke fired 25 MW steam plants.

Firm’s Role: To provide expertise and guidance in collecting plant data, establishing a database of component information, screening critical piping systems for inspection, and compiling all information into a final report which will also serve as a manual for program guidance.

Status: Project complete, issued final report/manual and provided some training to plant personnel.

 

Project: Design & Engineering -  20 MVA Overhead Transmission Line

Dates: May 2002 to July 2002

Description: Green field construction of an overhead power line to connect a new generating facility with an existing generating facility and substation.

Firm’s Role: To provide civil and electrical engineering services for the design and permitting of the power line.

Status: Project complete, construction drawings issued.

 

Project: Design and Engineering -  2.4 MW and 6.0 Landfill Gas Generating Facility

Dates: February 2002 to October 2002

Description: Green field construction of multiple modularized reciprocating gas engines to provide base load power consuming gas produced by the landfill.

Firm’s Role: To provide civil, electrical, and mechanical engineering services for the design and permitting of the power plants.

Status: Project complete.

2001   2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  - Back to Top

Project: Design & Engineering -  2.4 MW Stand-by Power Plant

Dates: November 2001 to February 2002

Description: Retrofit construction of a dual reciprocating gas engine plant for local sanitary district treatment plant to supply power for backup and to the California Independent System Operator during peek demand times.

Firm’s Role: To provide civil, architectural, mechanical, and electrical engineering services along with field and logistical support for the design, construction, commissioning of the power plant.

Status: Project complete

 

Project: Design and Engineering - 3 MW Standby Generating Facility

Dates: October 2001 to December 2001

Description: Green field construction of a single reciprocating gas engine plant to provide semiconductor manufacturing plant with standby power.

Firm’s Role: To provide mechanical engineering services for development of piping and instrumentation diagrams, material lists, and buried natural gas line design and limited field support for construction of the standby plant.

Status: Project complete.

 

Project: Design and  Engineering -  5 MW Power Plant

Dates: August 2001 to October 2001

Description: Green field construction of a dual reciprocating gas engine plant for local utility to supply power for local community.

Firm’s Role: To provide civil, architectural, and mechanical engineering services for the design and permitting of the power plant.

Status: Project complete.

 

Project: Design and Engineering -  8 MW Power Plant

Dates: July 2001 to Present

Description: Green field construction of a 7 reciprocating gas engine plant for local utility to supply power for snow making in local ski resorts.

Firm’s Role: To provide civil, architectural, mechanical, and electrical engineering services along with field and logistical support for the design, construction, commissioning of the power plant.

Status: Project complete.

 

Project:  Design and Engineering -  46 MW Peeking Power Plant

Dates: March 2001 to September 2001

Description: Green field construction of a 16 reciprocating gas engine plant to generate on-demand power for California’s Independent System Operator during peek demand times.

Firm’s Role: To provide civil, architectural, mechanical, and electrical engineering services along with field and logistical support for the design, construction, commissioning of the power plant.

Status: Project nearing completion, as-built review of completed plant in progress.

2000    2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  - Back to Top

Project: Design and Engineering -  48 MW  Power Plant

Dates: December 2000 to May 2001

Description: Green field construction of a 16 reciprocating gas engine plant to generate on-demand power for California’s Independent System Operator during peek demand times.

Firm’s Role: To provide civil, architectural, mechanical, and electrical engineering services along with field and logistical support for the design, construction, commissioning of the power plant.

Status: Project complete, plant went online one month prior to schedule.

 

Project: Development of a Reliability Centered Maintenance (RCM) Program For a Geothermal Power Plant

Dates: February 2000 to September 2001

Description: A DOE funded project to development for the first time a reliability centered maintenance program for a geothermal power plant in an effort to make renewable energy production more competitive.

Firm’s Role: To provide managerial and technical support in the development of this program. Tasks to include identifying a suitable database program and condition monitoring equipment, provide guidance on plant asset hierarchy development and asset prioritization, and any engineering support necessary to evaluate equipment condition and develop inspection intervals.

Status: Project complete.

 

Project: Analysis and Solutions - Evaluation of  a University  Medical Center Main Hospital Condensate Return

Dates: February 2000 to March 2000

Description: Evaluate existing condition of the Main Hospital condensate piping system, determine possible effects it could have on Central Plant performance, and recommend mitigative solutions to prevent any damage to Central Plant components.

Firm’s Role: To identify current condition of Main Hospital Condensate, evaluate condensate return system, and specify piping changes and a chemical treatment system.

Status: Project complete. Submitted condensate analysis results, recommended changes to return system, and specified a chemical treatment system for the Main Hospital to the client.

 

Project: Research & Development - Development of a Thermal Sag Mitigator for Transmission Lines

Dates: July 1999 to 2001

Description: Research, development, and demonstration of a device to mitigate thermal line sag in transmission lines.

Firm’s Role: Perform all engineering aspects to develop a sagging line mitigator device for prototyping and demonstration.

Status: Project underway. Scale prototypes have been built and proof of concept demonstrated. Full scale commercial version of device is under final development.

1999   2007 - 2006 -  2005 -   2004 -  2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  - Back to Top

Project: Analysis and Solutions/Design and Engineering of a Bed Removal System Upgrade

Dates: April 1999 to August 1999

Description: Evaluate existing fluidized bed removal system and design an upgrade to the system to eliminate thermal and corrosion related problems and improve safety.

Firm’s Role: To investigate and determine causes for current removal system problems and design an upgrade to the system by optimizing piping arrangement, piping components, piping material, and operational procedures.

Status: Project complete. Submitted construction drawings and operational procedures to client.

 

Project: Analysis and Solutions - Investigating Bearing Failures in Gas Turbines

Dates: March 1999 to May 1999

Description: To determine the root causes for the failure of and the high operating temperature of gas turbine bearings in several units.

Firm’s Role: Gather required data from OEM, operating history, and inspection reports to determine the root causes for the bearing problems and propose future activities to alleviate problem.

Status: Project complete. Submitted report identifying the lube oil system as probable cause for bearing problems.

 

Project: Analysis and Solutions - Life Assessment of a Reaction Turbine in a Compressor Gas Turbine

Dates: February 1999 to March 2000

Description: Gather required data and oversee the development of models to assess the condition of RT for its life extension by another firm.

Firm’s Role: Gather required data and information needed to oversee a life assessment/extension evaluation for the reaction turbine to delay overhaul and replacement activities.

Status: Project complete. Approved work completed by another firm to model and assess the condition of the RT.

 

Project: Analysis and Solutions - Investigating the Use of an Isolation Sealant to Protect Turbine Rotor Blade-Fits

Dates: January 1999 to April 2000

Description: Research into finding a suitable sealant either by locating an existing product or by formulating a new product that demonstrate the necessary properties to seal a blade-fit area of a geothermal turbine rotor against a high temperature corrosive environment.

Firm’s Role: Performed survey of geothermal operators to assist in developing universal sealant specifications, searched and acquired existing candidate sealants from industry. Performing field and lab tests to assess each candidate sealants applicability and issue report on findings.

Status: Project complete. Report submitted to DOE on results of project.

 

Project: Mitigating Corrosion Related Damage in Geothermal Facilities

Dates: July 1998 to August 2000

Description: Research into developing technology and methodology to mitigate debilitating forms of corrosion related damage from occurring in geothermal power plants.

Firm’s Role: Designed and constructed a portable corrosion research field lab to test various monitoring technologies at different geothermal sites, develop and test monitoring technologies for further research.

Status: Project complete. Report submitted to DOE on results of project.

1998  2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  - Back to Top

Project: Analysis and solutions - Nozzle Cracking Study for Gas Turbine Compressors

Dates: March 1996 to December 1998

Description: A comprehensive detailed analysis of nozzle cracking problem for gas turbine compressors.

Firm’s Role: Performed detailed 1-D fluid dynamics and heat transfer analysis to support state-of-the-art 3-D finite element non-linear analyses of nozzle models to investigate causes to the nozzle cracking problem.

Status: Project complete. Issued report on ground breaking discoveries into the operating condition of the gas turbine compressors, preparing to publish an article addressing this issue with the gas transmission industry.

 

Project: Analysis and Solutions - Condition Assessment of a Turbine Rotor

Dates: January to June 1998

Description: Stress analysis of Tiwi Unit #6 3rd stage for current condition and options to reduce operating stresses.

Firm’s Role: Developed finite element models of original stage design and current condition, perform stress analyses of developed models to determine operating stresses, and conduct a preliminary investigation into options which will reduce operating stresses.

Status: Project complete. Analyses were performed and results were compiled in a report. Recommendations were made as to which options would benefit the condition of the rotor best.

 

Project: Design Evaluation of an Electronic Ball Grid Array Contactor

Dates: October 1997 to May 1998

Description: Design review of a proprietary electronic contactor for testing electronic circuit boards using ball grid arrays.

Costs: $15K

Firm’s Role: Modeled and analyzed using finite element techniques the proprietary contactor design shapes for acceptability with ball grid array constraints.

Status: Project complete. Analyses identified problems with all proposed contactor shapes and material selection. Recommendations were made to develop a working design for the contactor.

1997      2007 - 2006 -  2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  - Back to Top

Project: Evaluation of a Fluidized Boiler Bed Removal System

Dates: November 1997 to December 1997

Description: Evaluate existing fluidized bed system and develop recommendations to alleviate the effect of system aging on process efficiency.

Firm’s Role: To investigate and determine causes for bed removal system problems and propose solutions to them.

Status: Project complete. Submitted final report identifying problem areas and proposed solutions to them.

 

Project: Analysis of a Coal De-Gasification Reactor

Dates: February to March 1997

Description: Design review of a proprietary coal charring process unit to determine compliance with mechanical and thermal loads.

Firm’s Role: Performed finite element analysis to determine mechanical and thermal stress levels and compared with allowable levels. Specified material & method of construction for assuring long term integrity.

Status: Project completed. Analysis identified problem areas in the reactor design for which recommendations were made for alternative designs and material selection.

 

Project: Research to Find Alternative Material for Encoder Tape

Dates: December 1996 to February 1997

Description: Research to improve the position measurement of automatic elevator encoder tape systems by evaluating the use of new materials and geometries for the encoder tapes.

Firm’s Role: Conducted research into lower cost tape materials which still met required performance criteria and different geometrical designs for the encoder tape.

Status: Project completed. Research concluded that no alternative cost effective materials existed for this application, recommended new geometrical designs for consideration.

 

Project: Bolt/Stud Ultrasonic Testing Research

Dates: May to September 1997

Description: Development of field inspection techniques to detect flaws or cracks in critical bolt studs of reciprocating engines and compressors.

Firm’s Role: Identified bolts and studs critical to system operation, estimated flaw sizes for inspection/detection by Ultrasonic Testing (UT) on review of historical data, developed reliable manual UT inspection technique, field testing and training for maintenance personnel, and coordination, final report, and project management.

Status: Project complete. Final report issued with inspection technique recommendations and training procedures.

 

Project: Non-Intrusive Alternatives to Reciprocating Compressor Overhaul

Dates: August to September 1997

Description: Continuation of previous work in addressing the condition based maintenance program for reciprocating compressor and critical components not accessible for non-intrusive inspection.

Firm’s Role: Reviewed past overhaul activities and OEM recommended inspections and developed a list of all components inspected. A description of potential failure and failure consequences was compiled for each of the components on the list.

Status: Project complete. Final report issued containing revised condition based maintenance program including all newly identified critical components and recommendations on implementation of revised program.

 

Project: Heat Shield Failure at Burney K-2 Compressor Station

Dates: April to May 1997

Description: An evaluation of a heat shield failure in a gas turbine compressor.

Firm’s Role: Performed an investigation of heat shield component failures by field inspection and review of operation and overhaul histories to identify causes for failure and make recommendations for future prevention.

Status: Project complete. Report issued detailing causes of failure and corrective actions needed to prevent recurrence of problems.

1996/..    2006 - 2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..   - Back to Top    

Project: Support of Acoustic Emission Research

Dates: June to August 1996

Description: To develop stress time histories at selected locations of a Primary Superheat Outlet Header of the Unit 6 Boiler at PG&E’s Pittsburg Power Plant for operational and field testing events.

Firm’s Role: Developed finite element models of super heater header to be used with field gathered operational data to perform simulations to compare results against acoustic emission monitoring results.

Status: Project complete. Full report issued with all results compiled for comparison.

 

Project: Plant Process and Equipment Review to Reduce Maintenance and Production Cost

Dates: February to March 1996

Description: Review and evaluation of an aluminum can manufacturing plant’s heavy equipment and recommendations to reduce maintenance and production costs.

Firm’s Role: Performed field inspections of equipment, interviewed equipment operators, reviewed OEM manuals and drawings, and reviewed process history to make recommendations to the plant engineering staff on equipment condition and developing a condition based maintenance program.

Status: Project complete. Issued full report on results and recommendations.

Project: Study of Non-Intrusive NDE Methods for Reciprocating Compressors and Pressure Vessels’ Condition based Maintenance Program

Dates: September to December 1996

Description: To review PG&E’s reciprocation gas compressors’ condition based maintenance program to identify critical components left off and investigate non-intrusive NDE methods to asses the condition of these components.

Firm’s Role: Identified compressor components of major concern and failure potential, identified components to be added to condition based maintenance program, identified needs for new time-based inspection intervals over and above existing program, and identified areas for research to further improve the current inspections and make them capable of assessing the condition of all major components of a reciprocating compressor.

Status: Project complete. Issued full report describing all findings, recommendations to continue research to develop NI-NDE tools for major compressor components.

 

Project: Evaluating Scanning Thermography technology for Use as an NDE Tool

Dates: January to December 1996

Description: To monitor and evaluate a new NDE technology, scanning thermography, for its potential use to exam power plant boiler wall and superheated tubes for damage.

Firm’s Role: Contacted and worked with vendor to understand and learn about the technology and conduct testing on tube samples for evaluation. Also researched the technology independently of the vendor for further evaluation.

Status: Project complete. Issued final report summarizing findings and recommending future activities to develop and demonstrate scanning thermography for PG&E’s boiler water wall inspections.

 

Project: Causes and Behavior of Internal and External Stub weld Cracks

Dates: January 1995 to April 1996

Description: Research was performed to investigate stub weld failures in power plant boiler headers and determine the root cause for these failures.

Firm’s Role: Develop techniques to model internal and external cracks in stub welds, study stub weld crack behavior under different operating conditions, determine effect of ligament cracks, and various operations on stub weld cracking, and determine interaction between external and internal stub weld cracks.

Status: Project Complete. Issued full report describing root cause for internal and external stub weld cracking and recommendations for further research into the root cause and methods for mitigation.

 

Project: De-Superheating Alternatives Project of  a  Power Plant

Dates: October 1994 to May 1996

Description: Research to determine and develop methods/technology to replace existing steam scrubbing technology with a more cost effective and energy efficient process.

Firm’s Role: Designed, fabricated, installed, tested, and verified a portable lab for The Geysers capable of simulating steam turbine conditions at first moisture. Assembled rotor steel modified wedge opening load coupons with load bolt and back face strain gages for continuous crack growth measurement and with various noble metals as corrosion potential probes. Developed a test plan and tested to identify steam conditions leading to stress corrosion cracking of rotor steel.

Status: PG&E’s sponsorship of project completed in 1996. Testing has resumed under sponsorship of the U.S. Department of Energy with cooperative efforts from PG&E and UNOCAL.

 

Project: Re-Inspection Interval for a Power Plant  Hot Reheat Piping

Dates: December 1995 to January 1996

Description: Provided information needed to establish re-inspection intervals for  Power Plant Unit 3 seam-welded hot reheat piping. Project utilized current remaining life estimating software and guidelines.

Firm’s Role: To evaluate each state-of-the-art software program for applicability to client’s problem and apply results to determine proper re-inspection intervals.

Status: Project completed. Re-inspection intervals were implemented to reduce unnecessary maintenance costs and increase reliability and safety.

 

Project: Evaluation of the Unit #12 Main Steam Shock Event

Dates: March 1996

Description: Performed cursory evaluation of the Unit 12 main steam line which suffered a transient during start-up and advised plant operators on areas for inspection.

Firms Role: Field inspections, review of piping and support layout, shock load calculations, and recommendations to prevent recurrence of similar events.

Status: Project completed. Further investigation pursued by client following our recommendations.

 

Project: Design, analysis, and construction management of an offshore fuel stripping system to remove diesel and heavy fuel.

Dates: Mid 94 to January 1996

Description: Design and engineer a new fuel stripping system for the offshore facility for the Potrero power plant to assure environmentally safe and reliable operations.

Firms Role: Design and engineered complete piping system/supports, specified pumping and valving requirements and developed complete operating procedures. Acted as construction management for installation and testing of the new system.

Status: Project completed. System installed and tested successfully.

Contact Us        2007-  2006 - 2005 -   2004 -   2003 -  2002 - 2001 - 2000 - 1999 - 1998 - 1997 - 1996/..  

- Back to Top      


 

   
 
     

Copyright © 2006 misolution.com All Rights Reserved